Rarely. The new design's footprint, loads, basement height and waterproofing almost always call for a new foundation, and only the engineer can approve keeping any part of the old one.

It is still a fair question to ask, and the answer depends on what the engineer finds.

Basement slab broken into rubble between marked block walls
Basement slab broken into rubble between marked block walls

What the engineer checks

If keeping the foundation is on the table, the structural engineer looks at whether it can carry the new house and meet current expectations. That usually includes:

  • Footing size and depth compared with the new loads.
  • The condition of the walls: cracks, bowing, spalling and signs of water.
  • The existing basement height against what the new design wants.
  • Whether waterproofing and drainage can be brought up to standard.

Why a keep often becomes a full removal

Many foundations look fine from inside a finished basement. Once the house comes down and the walls are exposed, problems that were hidden behind drywall, parging or soil become obvious. Cracks, poor footings or deteriorated block can turn a plan to keep the foundation into a plan to remove it.

It helps to agree with the builder in advance what happens if that turns out to be the case, so the schedule has room for it.

A partial keep

Sometimes the engineer approves keeping part of the foundation, such as one wall or a section under a garage. In that case, the demolition crew:

  • Marks the kept section clearly before work starts.
  • Removes the rest by working away from it, not toward it.
  • Breaks concrete near the kept section by hand or with small tools to avoid cracking it.
  • Reports any damage or surprises to the engineer immediately.

The permit drawings decide

Whatever the engineer recommends ends up on the drawings that Town of Oakville Building Services reviews for the new house permit, and those drawings govern what the crew keeps or removes.

What Bolan does either way

If the foundation is coming out, we break out the walls, footings and slab and haul them away through our foundation removal service. If part of it stays, we plan the demolition around the kept section, protect it as we work, and stop to call the engineer if anything looks wrong. For work on bearing walls or other load-carrying parts that stay, see our structural demolition service. Request a free estimate to go over your drawings.

Frequently asked questions

Would reusing the foundation save time on my rebuild?
It can seem that way, but the savings often disappear once the engineer's review, repairs and design limits are counted. A new foundation gives the designer more freedom and removes uncertainty about hidden problems. The engineer and builder can tell you whether keeping it makes sense for your project.
Can I keep the basement walls and raise the ceiling height?
Not by keeping the same walls as they are. A taller basement usually means deeper footings and new walls, since the existing ones were built for the original height. Some designs underpin or extend existing walls, but that is a specialised structural approach that needs the engineer's design.
What if cracks appear after the house comes down?
The crew stops work near the affected area and tells the owner, builder and engineer. The engineer then decides whether the section can still be kept, needs repair or should be removed. It is common for exposed walls to reveal problems that were hidden while the house was standing.
Who decides whether any foundation stays?
The structural engineer, and the decision is shown on the drawings submitted for the new house permit. The demolition contractor follows those drawings. Without an engineer's approval, the standard approach on an Oakville rebuild is to remove the old foundation completely.

Talk to us about your project